In this image Phases I, II, and III are on the right side of Rife Street and
Phase IV is on the left side.
The two Phase IV homes under construction can be seen to be almost complete.
Rife Street - 2025
Click image for a larger view.
Building Rife Street
As a part of the Blacktail Solar Homes Subdivision application, though long existing on a Dillon map, Rife Street
actually had to be built, together with installation of water and sewer lines in the street. An agreement was reached
with the City of Dillon wherein the developer constructed the road to the point where it is now ready for the asphalt paving.
Dillon will reimburse for the construction as well as provide the asphalt paving. Rife Street is currently waiting for the paving which is expected to be financed by a City Special Improvement District.
Images that follow show the construction as it happened: